    4000 psi Concrete Design Mix (≈28 MPa)

    Typical per-m³ quantities for 4000 psi structural concrete for footings, columns, beams and slabs. Indicative trial-mix starting point only. Final proportions must come from a lab trial mix (ACI 211.1) using your actual cement, sand and aggregate, approved by the consultant.

    Reference standards: ACI 211.1, ACI 318, ASTM C39

    MaterialPer m³Notes
    Cement (OPC)380 kg (7.6 bags)Grade 42.5
    Water175 Lw/c ≈ 0.46
    Sand720 kgFM 2.6–2.9
    Coarse aggregate 20 mm1,080 kg
    Plasticizer0.8–1.0% of cementPer supplier
    Nominal ratio≈ 1 : 1.5 : 3Reference only

    Mixing & application

    1. Get cement, sand, aggregate and admixture tested and approved before the trial for 4000 psi.
    2. Correct the water for aggregate moisture and absorption on the day of mixing.
    3. Batch by weight: aggregate, sand, cement, then 80% of water, admixture, remaining water.
    4. Mix in a drum or batching plant for at least 2 minutes until uniform.
    5. Check slump (target 100–125 mm) and temperature at the point of placing.
    6. Cast 6 cylinders (150×300 mm) per trial; test 3 at 7 days and 3 at 28 days.
    7. Target mean strength f'cr = f'c + 1.34s or f'c + 8.3 MPa when no history exists; adjust and repeat if short.

    Acceptance criteria

    • No single cylinder below f'c − 3.5 MPa.
    • Average of 3 consecutive tests ≥ 27.6 MPa.

    Health & safety

    • Wear PPE: helmet, safety shoes, gloves and eye protection.

    FAQs

    What is the 4000 psi Concrete Design Mix (≈28 MPa) used for?

    Typical per-m³ quantities for 4000 psi structural concrete for footings, columns, beams and slabs. Indicative trial-mix starting point only. Final proportions must come from a lab trial mix (ACI 211.1) using your actual cement, sand and aggregate, approved by the consultant.

    Which standard does it follow?

    It is based on ACI 211.1, ACI 318, ASTM C39. Always follow your project specification where it differs.

    Can I print or submit this?

    Yes. Use Print / PDF, add your project details and submit it through your normal approval process. Get it reviewed by your engineer or consultant first.

    Is it free?

    Yes. The library is free to read and print, without an account.

    General guidance only, not engineering advice. Project specifications, approved drawings, manufacturer data sheets and your consultant's instructions take priority. See our Policy. This document was generated using CM PRO. Powered by CM PRO.