Estimating & Cost calculator

    PEC / FIDIC Price Escalation

    The free PEC / FIDIC Price Escalation by CM PRO helps site engineers, quantity surveyors, contractors and homeowners iPC price adjustment from editable material weightages and Lo/Ln indices. It supports both metric and imperial units and gives instant results for calculating PEC and FIDIC Sub-Clause 13.8 price adjustment on interim payment certificates using cement, steel, diesel, labour, bitumen or custom indices.

    How the PEC / FIDIC Price Escalation works

    PEC / FIDIC adjustment factor Pn = A + Σ[bᵢ × (Ln ÷ Lo)]. Escalation = IPC × Σ[bᵢ × (Ln ÷ Lo − 1)], where A is the fixed non-adjustable portion and A + Σbᵢ must equal 100%.

    How to use this calculator

    1. Sign up free and verify your email to unlock the calculator.
    2. Choose Metric (m, mm, m³, kg) or Imperial (ft, in, cft, lb) units.
    3. Enter the base rate, base index, current index, escalable portion.
    4. Results update instantly — read the quantities in the Results panel.
    5. Add a wastage allowance and confirm against your drawings and specifications before ordering.

    Typical uses

    Calculating PEC and FIDIC Sub-Clause 13.8 price adjustment on interim payment certificates using cement, steel, diesel, labour, bitumen or custom indices.

    Assumptions & limitations

    Results are planning estimates based on standard assumptions for estimating & cost work. They do not replace structural design, site measurement or project specifications. Material densities, wastage and mix proportions vary by region and supplier.

    Frequently asked questions

    How does the PEC / FIDIC Price Escalation work?
    PEC / FIDIC adjustment factor Pn = A + Σ[bᵢ × (Ln ÷ Lo)]. Escalation = IPC × Σ[bᵢ × (Ln ÷ Lo − 1)], where A is the fixed non-adjustable portion and A + Σbᵢ must equal 100%.
    Can I use the PEC / FIDIC Price Escalation in feet and inches?
    Yes. Switch to Imperial and enter feet, inches, square feet or pounds — the calculator converts automatically and shows results in imperial units.
    When should I use the PEC / FIDIC Price Escalation?
    Calculating PEC and FIDIC Sub-Clause 13.8 price adjustment on interim payment certificates using cement, steel, diesel, labour, bitumen or custom indices.
    Is this construction calculator free?
    Yes. All CM PRO construction calculators are free — you only need to sign up and verify your email.

    Related searches: PEC price escalation calculator Pakistan, FIDIC 13.8 calculator, IPC price adjustment formula, construction cost index escalation, cement steel diesel labour indices.