    Plate Load Test

    Field test to estimate the bearing capacity and settlement of soil at foundation level.

    Reference standards: ASTM D1194 / IS 1888

    Equipment

    • 300–750 mm steel plate
    • Hydraulic jack & pressure gauge
    • Reaction load (kentledge)
    • Dial gauges (0.01 mm)

    Procedure

    1. Excavate to foundation level; pit width at least 5 × plate width.
    2. Seat the plate on a thin sand layer and set the jack and dial gauges.
    3. Apply a seating load and zero the gauges.
    4. Apply load in equal increments (≈ 1/5 of expected capacity), holding until settlement stabilises.
    5. Continue to failure or 25 mm settlement; record load–settlement data and plot.

    Acceptance criteria

    • Allowable bearing pressure from the curve with factor of safety (typically 2.5–3) and settlement limits.

    Health & safety

    • Wear PPE: helmet, safety shoes, gloves and eye protection.
    • Keep clear of the kentledge during loading.

    FAQs

    What is the Plate Load Test used for?

    Field test to estimate the bearing capacity and settlement of soil at foundation level.

    Which standard does it follow?

    It is based on ASTM D1194 / IS 1888. Always follow your project specification where it differs.

    Can I print or submit this?

    Yes. Use Print / PDF, add your project details and submit it through your normal approval process. Get it reviewed by your engineer or consultant first.

    Is it free?

    Yes. The library is free to read and print, without an account.

    General guidance only, not engineering advice. Project specifications, approved drawings, manufacturer data sheets and your consultant's instructions take priority. See our Policy. This document was generated using CM PRO. Powered by CM PRO.