Planning tools

    Sample schedule (demo) · read in your browser only, never uploaded

    Health score

    23%

    Activities

    10

    Relationships

    8

    Data date

    2026-06-01

    #CheckResultLimitStatus
    1

    Missing logic (open ends)

    Incomplete activities with no predecessor or no successor. Open ends let dates float freely, hide the true critical path and make float meaningless.

    Fix: Give every activity at least one predecessor and one successor; only the project start and finish milestones may have an open end.

    e.g. A1060 MEP first fix; A1080 Site boundary wall; A1090 Practical completion

    %≤ 5%Fail
    2

    Leads (negative lags)

    Relationships with a negative lag let a successor start before its predecessor finishes and distort the critical path.

    Fix: Replace a lead with a start-to-start link plus a positive lag, or split the predecessor into parts.

    e.g. 7

    count0Fail
    3

    Positive lags

    Lags are hidden durations. Curing, approvals or delivery time placed in a lag cannot be statused or resourced.

    Fix: Model waiting time as a real activity (e.g. 'Concrete curing 7d') so it is visible and can be updated.

    e.g. 5

    %≤ 5%Fail
    4

    Non finish-to-start relationships

    A schedule built mainly on SS/FF/SF links is hard to follow and often hides overlapping logic errors.

    Fix: Use finish-to-start as the default; keep SS/FF only where work genuinely overlaps.

    e.g. 7

    %≤ 10% (≥ 90% FS)Fail
    5

    Hard constraints

    Mandatory start/finish and start-on/finish-on constraints override logic and can create false float or hide delay.

    Fix: Remove hard constraints and drive dates with logic; use soft 'start on or after' only for genuine external dates.

    e.g. A1070 Finishes

    %≤ 5%Fail
    6

    High total float (> 44 working days)

    Very high float usually means missing successors, not genuine flexibility.

    Fix: Check the successors of these activities and tie them to the work that really needs them.

    e.g. A1060 MEP first fix; A1080 Site boundary wall

    %≤ 5%Fail
    7

    Negative float

    Negative float shows the forecast finish is later than a constraint or deadline — the project is already late on that path.

    Fix: Prepare a recovery plan: re-sequence, add resources, fast-track or request an extension of time.

    e.g. A1030 Foundations; A1040 Superstructure frame G+4; A1050 Blockwork; A1070 Finishes

    count0Fail
    8

    High remaining duration (> 44 working days)

    Long activities are hard to measure and control; progress becomes a guess.

    Fix: Break long activities into measurable parts by area, floor or system (about one update period or a few weeks each).

    e.g. A1040 Superstructure frame G+4; A1070 Finishes

    %≤ 5%Fail
    9

    Invalid dates against the data date

    Actual dates after the data date, or forecast dates before it, mean the update was not scheduled correctly.

    count0Pass
    10

    Activities without resources

    Unresourced activities cannot support manpower histograms, cost loading or earned value.

    e.g. A1050 Blockwork; A1060 MEP first fix; A1070 Finishes; A1080 Site boundary wall

    %ReportN/A
    11

    Missed activities (baseline finish passed)

    Activities that should have finished by the data date but did not, or finished late — a direct measure of execution performance.

    Fix: Review causes, update forecasts honestly and add the late activities to the look-ahead and recovery plan.

    e.g. A1010 Mobilisation; A1020 Excavation; A1030 Foundations; A1080 Site boundary wall

    %≤ 5%Fail
    12

    Critical path continuity

    There should be a continuous chain of zero-float (or driving) activities from the data date to project completion.

    e.g. A1030 Foundations; A1040 Superstructure frame G+4; A1050 Blockwork; A1070 Finishes

    countContinuous pathPass
    13

    Critical Path Length Index (CPLI)

    CPLI = (critical path length + total float) ÷ critical path length. Remaining length 144 days, lowest float -5.0 days.

    index≥ 0.95Pass
    14

    Baseline Execution Index (BEI)

    BEI = activities completed ÷ activities planned to be complete by the data date (planned dates from the XER target dates).

    Fix: A low BEI shows the team is finishing less work than planned; investigate productivity, access, materials and approvals.

    index≥ 0.95Fail

    Consultants audit every programme before they accept it. Missing links, constraints and lags hide delay and make the critical path meaningless. This tool reads your P6 XER export in the browser — nothing is uploaded — and runs the fourteen checks reviewers use, with the reason and the fix for every failure.

    Why schedule quality matters

    A programme is a contract document under most standard forms: it is used to judge progress, extensions of time and acceleration. A schedule with open ends or hard constraints can show any finish date you want, so an engineer will reject it or, worse, accept it and use it against you in a claim.

    Logic checks (1–4)

    1) Missing logic: incomplete activities without a predecessor or successor, target ≤ 5%. 2) Leads: negative lags, target 0. 3) Lags: positive lags, target ≤ 5% of relationships. 4) Relationship types: finish-to-start should be at least 90% of links.

    Constraint, float and duration checks (5–8)

    5) Hard constraints (mandatory or 'on' dates) ≤ 5%. 6) High float above 44 working days ≤ 5% — usually a sign of missing successors. 7) Negative float: 0, otherwise the forecast already misses a constraint. 8) High duration: remaining durations above 44 working days ≤ 5%, because long activities cannot be measured reliably.

    Update and performance checks (9–14)

    9) Invalid dates: actuals after the data date or forecasts before it, target 0. 10) Resources: activities without resources (reported). 11) Missed tasks: activities planned to finish by the data date that did not, ≤ 5%. 12) Critical path continuity. 13) CPLI = (critical path length + total float) ÷ critical path length, target ≥ 0.95. 14) BEI = completed ÷ planned-to-complete activities, target ≥ 0.95.

    Privacy

    Your XER is read only in your browser memory. No schedule data is sent to CM PRO or stored on a server.

    Limits

    The tool reads standard P6 XER tables (PROJECT, TASK, TASKPRED, TASKRSRC). Planned dates for missed tasks and BEI use the XER target dates; if your contract baseline is a separate project, export it and compare. Thresholds are widely used guidelines; your contract or consultant may set different limits.

    How to use

    1. In P6 select the project and export it as an XER file.
    2. Upload the file here (or open the sample schedule).
    3. Review the score and each failed check with examples.
    4. Fix the schedule in P6, export again and re-check before submission.

    FAQs

    Is my schedule uploaded?

    No. The file is processed locally in your browser and is never sent to a server.

    Why 44 working days?

    44 working days is roughly two months — two typical monthly update cycles. Activities or float longer than that are hard to control and usually point to missing logic.

    Does a 100% score mean the schedule is right?

    No. The checks find structural problems. The logic, durations and resources must still reflect the real construction method.

    Learn it properly