Consultants audit every programme before they accept it. Missing links, constraints and lags hide delay and make the critical path meaningless. This tool reads your P6 XER export in the browser — nothing is uploaded — and runs the fourteen checks reviewers use, with the reason and the fix for every failure.
Why schedule quality matters
A programme is a contract document under most standard forms: it is used to judge progress, extensions of time and acceleration. A schedule with open ends or hard constraints can show any finish date you want, so an engineer will reject it or, worse, accept it and use it against you in a claim.
Logic checks (1–4)
1) Missing logic: incomplete activities without a predecessor or successor, target ≤ 5%. 2) Leads: negative lags, target 0. 3) Lags: positive lags, target ≤ 5% of relationships. 4) Relationship types: finish-to-start should be at least 90% of links.
Constraint, float and duration checks (5–8)
5) Hard constraints (mandatory or 'on' dates) ≤ 5%. 6) High float above 44 working days ≤ 5% — usually a sign of missing successors. 7) Negative float: 0, otherwise the forecast already misses a constraint. 8) High duration: remaining durations above 44 working days ≤ 5%, because long activities cannot be measured reliably.
Update and performance checks (9–14)
9) Invalid dates: actuals after the data date or forecasts before it, target 0. 10) Resources: activities without resources (reported). 11) Missed tasks: activities planned to finish by the data date that did not, ≤ 5%. 12) Critical path continuity. 13) CPLI = (critical path length + total float) ÷ critical path length, target ≥ 0.95. 14) BEI = completed ÷ planned-to-complete activities, target ≥ 0.95.
Privacy
Your XER is read only in your browser memory. No schedule data is sent to CM PRO or stored on a server.
Limits
The tool reads standard P6 XER tables (PROJECT, TASK, TASKPRED, TASKRSRC). Planned dates for missed tasks and BEI use the XER target dates; if your contract baseline is a separate project, export it and compare. Thresholds are widely used guidelines; your contract or consultant may set different limits.
How to use
- In P6 select the project and export it as an XER file.
- Upload the file here (or open the sample schedule).
- Review the score and each failed check with examples.
- Fix the schedule in P6, export again and re-check before submission.
FAQs
Is my schedule uploaded?
No. The file is processed locally in your browser and is never sent to a server.
Why 44 working days?
44 working days is roughly two months — two typical monthly update cycles. Activities or float longer than that are hard to control and usually point to missing logic.
Does a 100% score mean the schedule is right?
No. The checks find structural problems. The logic, durations and resources must still reflect the real construction method.