A single-number duration hides uncertainty. PERT asks for three estimates and turns them into a probability: how likely are we to finish by the date promised in the tender? This tool calculates every PERT figure for the activities on your critical path and the contingency you need for a chosen confidence level.
The three estimates
Optimistic (O): the duration if everything goes right — materials on time, good weather, approvals first time. Most likely (M): the realistic duration under normal conditions. Pessimistic (P): the duration if credible problems occur, excluding catastrophes. Always O ≤ M ≤ P.
Beta (PERT) and triangular means
PERT expected time TE = (O + 4M + P) ÷ 6, which gives the most likely value four times the weight of the extremes. The triangular mean (O + M + P) ÷ 3 gives equal weight and is more conservative when the pessimistic tail is long. The tool shows both so you can compare.
Standard deviation and variance
Activity standard deviation σ = (P − O) ÷ 6 and variance = σ². For a path, add the variances (not the deviations) and take the square root: σpath = √Σσ². This assumes the activities are independent.
Probability of meeting a target
Z = (Target − ΣTE) ÷ σpath. The probability of finishing on or before the target is the area under the standard normal curve up to Z: Z = 0 → 50%, Z = 1 → 84.1%, Z = 1.645 → 95%, Z = 2 → 97.7%. A negative Z means the target is earlier than the expected finish.
Contingency reserve
The duration at a confidence level is ΣTE + z × σpath (z = 1.2816 for 90%). The difference between that duration and the deterministic plan (sum of most likely durations) is the schedule contingency you should protect in the programme or a buffer activity.
Worked example
Piling O 10, M 14, P 24 days: TE = (10 + 56 + 24) ÷ 6 = 15.0 days, σ = 14 ÷ 6 = 2.33 days. For a target of 17 days, Z = (17 − 15) ÷ 2.33 = 0.86 → about 80% probability.
How to use
- List the critical-path activities (or work packages) in sequence.
- Enter O, M and P durations for each.
- Enter the target duration and the confidence level you need.
- Read the probability, the duration at that confidence and the contingency.
FAQs
Should I include non-critical activities?
For a quick PERT probability use the critical path. Near-critical paths can also become critical; a full Monte Carlo simulation handles that, but PERT is the standard first check.
Is PERT the same as Monte Carlo?
No. PERT uses one path and the normal approximation. Monte Carlo simulates thousands of runs across the whole network. PERT is faster and is used in exams, tenders and early planning.
What confidence should a contractor use?
Many contractors price at 80–90% confidence (P80–P90) for critical milestones that carry delay damages.