    BAC × physical % complete

    Fresh estimate of remaining cost

    CPI

    0.921

    SPI

    0.875

    Cost variance CV

    -1,500,000

    Schedule variance SV

    -2,500,000

    % complete (EV/BAC)

    35.0%

    % spent (AC/BAC)

    38.0%

    TCPI to BAC

    1.048

    TCPI to EAC (CPI)

    0.921

    Estimate at completion — four forecasts

    Atypical — remaining at budget rate (AC + (BAC − EV))51,500,000
    Typical — current CPI continues (BAC ÷ CPI)54,285,714
    Cost & schedule pressure (AC + (BAC − EV) ÷ (CPI × SPI))59,326,531
    Bottom-up re-estimate (AC + new ETC)enter ETC
    Budget (BAC) 50,000,000

    ETC (typical)

    35,285,714

    VAC (typical)

    -4,285,714

    Forecast duration ≈ planned ÷ SPI

    20.6 months

    Cost: CPI 0.92 — behind — corrective action. Every 1.00 spent is earning 0.92 of budgeted work.

    Schedule: SPI 0.88 — critical — recovery plan required. Confirm the date forecast with the CPM schedule; SPI drifts back to 1.00 as a late project finishes.

    Achievability: to finish within BAC the remaining work must run at a CPI of 1.05, well above current performance — revise the EAC and inform management.

    CPI and SPI tell you where you are; forecasting tells management where you will land. This tool calculates every standard earned value forecast so you can present a range of completion costs and the performance the team must achieve on the remaining work.

    The four inputs

    BAC (Budget at Completion) is the total approved budget. PV (Planned Value) is the budgeted cost of work scheduled to date. EV (Earned Value) is the budgeted cost of work actually performed (BAC × % physical complete). AC (Actual Cost) is the cost actually incurred for that work.

    Variances and indices

    CV = EV − AC (negative = over budget). SV = EV − PV (negative = behind schedule, in money). CPI = EV ÷ AC; SPI = EV ÷ PV. An index of 1.00 is on plan, above 1 is better, below 1 is worse.

    Four ways to forecast EAC

    1) Atypical variance — the problem will not recur and remaining work goes at budget rate: EAC = AC + (BAC − EV). 2) Typical — current cost efficiency continues: EAC = BAC ÷ CPI. 3) Cost and schedule pressure both persist (e.g. acceleration needed to hit a fixed date): EAC = AC + (BAC − EV) ÷ (CPI × SPI). 4) Bottom-up — the original estimate is no longer valid: EAC = AC + new ETC.

    ETC and VAC

    ETC (Estimate to Complete) = EAC − AC: money still needed. VAC (Variance at Completion) = BAC − EAC: the expected overrun (negative) or underrun at the end.

    TCPI — the reality check

    TCPI(BAC) = (BAC − EV) ÷ (BAC − AC): the cost efficiency needed on all remaining work to finish within the original budget. TCPI(EAC) = (BAC − EV) ÷ (EAC − AC) for a revised target. If TCPI is well above the current CPI (more than about 0.05–0.10 higher), finishing on budget is unrealistic and the forecast should be revised.

    Worked example

    BAC 1,000, PV 400, EV 350, AC 380. CPI = 0.921, SPI = 0.875. EAC typical = 1,000 ÷ 0.921 = 1,085.7; atypical = 380 + 650 = 1,030; CPI×SPI = 380 + 650 ÷ 0.806 = 1,186.5. TCPI(BAC) = 650 ÷ 620 = 1.048 — the team must perform about 14% better than now to stay on budget.

    How to use

    1. Enter BAC and the cut-off values for PV, EV and AC (same currency).
    2. Optionally add a bottom-up estimate to complete and the planned duration in months.
    3. Compare the four EAC values and choose the one whose assumption fits your project.
    4. Use TCPI to judge whether the budget is still achievable and print the forecast sheet.

    FAQs

    Which EAC should I report?

    Report the one whose assumption is true for your project, and state it. Many controllers show the CPI and CPI×SPI forecasts as a likely range.

    Where does EV come from on a construction site?

    From measured physical progress: quantities installed × budget rates, or weighted milestones. Never use cost spent as progress.

    Can SPI forecast the finish date?

    Roughly: forecast duration ≈ planned duration ÷ SPI. SPI tends to 1.0 at the end of a late project, so use the CPM schedule for the real forecast date.