CPI and SPI tell you where you are; forecasting tells management where you will land. This tool calculates every standard earned value forecast so you can present a range of completion costs and the performance the team must achieve on the remaining work.
The four inputs
BAC (Budget at Completion) is the total approved budget. PV (Planned Value) is the budgeted cost of work scheduled to date. EV (Earned Value) is the budgeted cost of work actually performed (BAC × % physical complete). AC (Actual Cost) is the cost actually incurred for that work.
Variances and indices
CV = EV − AC (negative = over budget). SV = EV − PV (negative = behind schedule, in money). CPI = EV ÷ AC; SPI = EV ÷ PV. An index of 1.00 is on plan, above 1 is better, below 1 is worse.
Four ways to forecast EAC
1) Atypical variance — the problem will not recur and remaining work goes at budget rate: EAC = AC + (BAC − EV). 2) Typical — current cost efficiency continues: EAC = BAC ÷ CPI. 3) Cost and schedule pressure both persist (e.g. acceleration needed to hit a fixed date): EAC = AC + (BAC − EV) ÷ (CPI × SPI). 4) Bottom-up — the original estimate is no longer valid: EAC = AC + new ETC.
ETC and VAC
ETC (Estimate to Complete) = EAC − AC: money still needed. VAC (Variance at Completion) = BAC − EAC: the expected overrun (negative) or underrun at the end.
TCPI — the reality check
TCPI(BAC) = (BAC − EV) ÷ (BAC − AC): the cost efficiency needed on all remaining work to finish within the original budget. TCPI(EAC) = (BAC − EV) ÷ (EAC − AC) for a revised target. If TCPI is well above the current CPI (more than about 0.05–0.10 higher), finishing on budget is unrealistic and the forecast should be revised.
Worked example
BAC 1,000, PV 400, EV 350, AC 380. CPI = 0.921, SPI = 0.875. EAC typical = 1,000 ÷ 0.921 = 1,085.7; atypical = 380 + 650 = 1,030; CPI×SPI = 380 + 650 ÷ 0.806 = 1,186.5. TCPI(BAC) = 650 ÷ 620 = 1.048 — the team must perform about 14% better than now to stay on budget.
How to use
- Enter BAC and the cut-off values for PV, EV and AC (same currency).
- Optionally add a bottom-up estimate to complete and the planned duration in months.
- Compare the four EAC values and choose the one whose assumption fits your project.
- Use TCPI to judge whether the budget is still achievable and print the forecast sheet.
FAQs
Which EAC should I report?
Report the one whose assumption is true for your project, and state it. Many controllers show the CPI and CPI×SPI forecasts as a likely range.
Where does EV come from on a construction site?
From measured physical progress: quantities installed × budget rates, or weighted milestones. Never use cost spent as progress.
Can SPI forecast the finish date?
Roughly: forecast duration ≈ planned duration ÷ SPI. SPI tends to 1.0 at the end of a late project, so use the CPM schedule for the real forecast date.