Extension of time disputes are rarely about whether a delay happened — they are about who caused it, whether it was on the critical path and what happened when both parties were late at the same time. This evaluator turns a delay log into an entitlement summary you can discuss with the engineer before you build the formal claim.
Three delay categories
Excusable and compensable: caused by the employer or its engineer (late drawings, access, instructions, suspension) — time plus money. Excusable and non-compensable: caused by neither party (exceptionally adverse weather, force majeure, changes in law where so stated) — time only. Non-excusable (culpable): caused by the contractor (low productivity, late subcontractors, plant breakdown) — no time, and delay damages may apply.
Only critical delays earn time
A delay extends completion only if it affects the critical path at the time it occurs. A delay on an activity with float is absorbed by the float first. Mark each event as critical only when your schedule analysis shows it drives the completion date.
Concurrency
Concurrent delay is when an employer delay and a contractor delay both affect completion over the same period. A widely followed approach is 'time but no money': the contractor receives the extension (so no delay damages) but no prolongation cost for the overlap. Some contracts and courts apportion the overlap; the tool can also show a 50/50 apportionment.
Money: prolongation and delay damages
Compensable days × daily time-related site overheads gives a first prolongation estimate (detailed claims also use head-office formulas such as Hudson, Emden or Eichleay). Delay damages = (project overrun − EOT days) × daily rate, limited to the contract cap — often 10% of the contract price.
Choosing a delay analysis method
Time Impact Analysis inserts a fragnet into the latest update — the standard for prospective EOT requests. Windows analysis splits the project into update periods. As-planned vs as-built compares the baseline with actual dates. Impacted as-planned adds delays to the baseline only. Collapsed as-built removes employer delays from the as-built programme. The selector ranks all five for your records and timing.
Notices first
Under FIDIC-based contracts the contractor must give notice within 28 days of becoming aware of the event, or lose entitlement. Keep contemporary records — daily reports, photos, correspondence and updated programmes — for every event in this log.
How to use
- Add each delay event with its responsible party and start/end dates.
- Tick 'critical' only for events that drove the completion date.
- Choose the concurrency approach and enter overrun, delay damage rate, cap and daily overheads.
- Read the EOT, compensable and culpable days, use the method selector and print the summary.
FAQs
Is this a substitute for a forensic delay report?
No. It organises facts and shows likely entitlement. A formal claim needs schedule analysis, records and the contract clauses.
What counts as a neutral event?
An event outside both parties' control that the contract treats as excusable, such as exceptionally adverse climatic conditions or force majeure. Check your contract — some risks are allocated to the contractor.
Why are concurrent days not paid?
Because the contractor would have been late anyway for its own reasons over that period. It is protected from delay damages but cannot recover the cost of time it also caused.