    Sand Blasting and Painting

    Crew size

    10 persons

    Key trade

    Painter 40%

    Crew for 1 Painter

    3 persons

    TradeShareExactPersons
    Painter40%4.004
    Helper25%2.503
    Sand Blaster15%1.501
    Foreman8%0.801
    Scaffolder8%0.801
    Rigger4%0.400
    Total10

    Whole persons are allocated by the largest-remainder method so the trades add up exactly to the crew size. Ratios are typical industrial practice; adjust to your site productivity records.

    A crew is not just a headcount. The right mix of foremen, skilled trades, riggers, scaffolders and helpers decides productivity and cost. This calculator uses a normalised catalogue of 458 industrial and civil activities with the share of each trade in a balanced crew, so you can size gangs, plan mobilisation and build manpower histograms.

    How the ratios work

    Each activity lists the percentage of the crew headcount for every trade. Example — concrete works in foundations: masons/concrete hands 75%, labour 15%, civil foreman 5%, scaffolders 5%. For a 20-person crew that is 15 masons, 3 labourers, 1 foreman and 1 scaffolder.

    Whole people, exact total

    People cannot be split, so the tool rounds with the largest-remainder method: every trade gets the whole number below its exact share, then the remaining places go to the largest fractions. The total always equals the crew size you enter.

    Sizing from a key trade

    Often the limiting resource is one trade — four certified welders or two crane riggers. Enter the available number for that trade and the tool works out the balanced crew size around it.

    Crew from quantity and output

    If you know the quantity, output per man-day and the days available, crew size = quantity ÷ (output per man-day × days), rounded up. Use your own measured productivity; outputs vary with site conditions.

    Disciplines covered

    Civil & architectural (excavation, concrete, masonry, formwork, flooring, fencing), piping (fabrication and erection by diameter and material — carbon, stainless and alloy steel — underground piping and hydrotests), tanks (API 650 fabrication and erection by part), mechanical equipment (pumps, compressors, turbines, furnaces, conveyors, kilns), structural steel, electrical, instrumentation, HVAC, and insulation & painting.

    Data notes

    Activity names were cleaned and duplicates removed. Percentages are kept exactly as recorded; two activities total 90–95% in the source and are flagged. Ratios are planning guidance — adjust to your method statement, safety requirements and local labour rules.

    How to use

    1. Search or filter by discipline and pick an activity.
    2. Enter the total crew size, or the number available in a key trade.
    3. Add the crew to your manpower sheet and repeat for other activities.
    4. Review the trade totals and print or save the manpower plan.

    FAQs

    Why does the foreman share look small?

    One foreman typically leads 10–20 people. In small crews the rounding may give zero; always appoint a responsible supervisor regardless of the calculated number.

    Can I use this for resource loading in P6?

    Yes. Use the trade split to create labour resources per activity, then load the man-days in P6 or the CM PRO Planning module.

    Does it give productivity rates?

    This catalogue gives crew mix only. For output rates use the CM PRO Productivity Planner or your own records.