Planning tools

    Activities & logic

    IDActivityDuration (days)Predecessors (e.g. A, B SS+2, C FF-1)

    Project duration

    38 days

    Critical path

    A → B → C → E → F → H → I

    Critical activities

    7 of 9

    IDActivityDurESEFLSLFTFFFCritical
    ASite clearance & layout3030300Yes
    BExcavation5383800Yes
    GBoundary wall1031328382525—
    CPCC & foundations881681600Yes
    DUnderground drainage459121677—
    EPlinth beam & backfill61622162200Yes
    FGround-floor columns72229222900Yes
    HRoof slab92938293800Yes
    IHandover milestone03838383800Yes
    033ASite clearance & layout003358BExcavation30831013GBoundary wall2825388816CPCC & foundations8016549DUnderground drainage1271616622EPlinth beam & backfill1602222729FGround-floor columns2202929938HRoof slab2903838038IHandover milestone38038

    Node key — top: ES · Duration · EF; centre: ID and name; bottom: LS · Total float · LF. Red = critical.

    Planning starts with logic, not software. If you can draw the network and run the forward and backward pass by hand, you can plan on paper, in Excel or in any scheduling package. This calculator does the passes for you instantly so you can check your manual answers, test what-if changes and see which activities really drive the finish date.

    Forward pass — earliest dates

    Start every activity without predecessors at day 0. For a finish-to-start link the successor's Early Start (ES) is the predecessor's Early Finish (EF) plus lag. Early Finish = ES + duration. When an activity has several predecessors, take the largest (latest) result, because the work cannot start until every predecessor allows it. The largest EF in the network is the project duration.

    Backward pass — latest dates

    Set the Late Finish (LF) of the last activities equal to the project duration and work backwards. For a finish-to-start link the predecessor's LF is the successor's Late Start (LS) minus lag; LS = LF − duration. With several successors take the smallest (earliest) result. This gives the latest dates each activity can occur without delaying completion.

    Total float and free float

    Total Float (TF) = LS − ES = LF − EF: how many days an activity can slip before the project finish moves. Free Float (FF) = the earliest start of the next activity − this activity's EF (for FS links): how many days it can slip without delaying any successor. Activities with zero total float form the critical path; negative float means the network already misses a constraint.

    Relationship types and lags

    FS (finish-to-start) is the normal case: B starts after A finishes. SS (start-to-start) lets B start a set time after A starts — e.g. blockwork 3 days after the frame starts on the next floor. FF (finish-to-finish) makes B finish a set time after A finishes — e.g. testing finishes 2 days after installation. SF (start-to-finish) is rare and used in shift handovers. A positive lag is a waiting time; a negative lag (lead) is an overlap and should be avoided in professional schedules.

    Worked example

    A Excavation 3 days; B Foundation 4 days after A; C Drainage 2 days after A; D Plinth 5 days after B and C. Forward pass: A 0–3, B 3–7, C 3–5, D 7–12. Project duration 12 days. Backward pass: D 7–12, B 3–7, C LF 7 so LS 5, A 0–3. C has TF = 5 − 3 = 2 days and FF = 7 − 5 = 2 days; the critical path is A → B → D.

    Day-number convention

    This tool uses the 'day 0' convention common in Excel and software: an activity occupies days ES to EF, and its successor can start on day EF. Some textbooks start at day 1 and subtract 1 for finishes; both give the same float and critical path.

    How to use

    1. Enter each activity ID, a description and its duration in working days.
    2. Type predecessors, e.g. A, B SS+2, C FF-1 (default is FS with zero lag).
    3. Press Calculate and read ES, EF, LS, LF, TF and FF in the table.
    4. Check the critical path and the network diagram, then print a calculation sheet.

    FAQs

    Can I learn planning without Primavera P6?

    Yes. CPM is a method, not a software feature. If you can run the forward and backward pass you can plan on paper or Excel; P6 only automates the same arithmetic for thousands of activities.

    What is the difference between total float and free float?

    Total float protects the project finish; free float protects the next activity. Using free float never delays anyone; using total float may consume float that a later activity needed.

    Why does my network show a loop error?

    A circular relationship (A → B → A) has no valid start date. Remove one of the links; real work always flows in one direction.

    How many activities can I enter?

    As many as you need for learning and small projects. For full project schedules use the CM PRO Planning module or import your P6 XER file.