Uncontrolled change is the fastest way to lose time and money. A formal change request records what changes, why, what it costs in time and money, which options were considered and who approved it — before the work is done. This generator produces a clean, numbered PCR ready for signature.
When to raise a change request
Raise a PCR for any change to approved scope, specification, drawings, quantities beyond tolerance, sequence, milestones or budget — whether requested by the client, designer, consultant or contractor. Under FIDIC-based contracts, a variation is instructed by the engineer; the PCR is the internal and pre-instruction record that evaluates it.
Reason codes
Client request (new or changed requirement); Design change or development; Error or omission in documents; Unforeseen site condition; Regulatory or authority requirement; Value engineering proposal; Force majeure or external event; Contractor proposal for method or sequence. One primary code keeps the change log analysable.
Impact analysis
Scope: what is added, omitted or changed. Schedule: days of delay or saving and whether the critical path is affected (support with a fragnet). Cost: direct cost, indirect cost and contingency used. Quality and risk: new risks, approvals and testing. Resources: labour, plant and materials.
Options and recommendation
List the alternatives considered — including 'do nothing' — with their impact, then the recommended option and why. Decision makers approve faster when trade-offs are visible.
Approval and implementation
The PCR moves from originator to project manager, consultant/engineer and client. Only after approval are the baseline, budget and drawings revised and the change log updated.
How to use
- Fill in project details, the change title and reason code.
- Describe the change and justify it.
- Enter time, cost, scope, quality and risk impacts and the options.
- Print the A4 PCR (sign-in required) and circulate for signature.
FAQs
Is a PCR the same as a variation order?
No. The PCR evaluates and requests the change; the variation order or engineer's instruction is the contractual authority to proceed.
Is my data saved?
Drafts stay in your browser only. Nothing is stored on a server.
Can I use it for internal changes?
Yes — method, sequence, resource or budget re-allocation changes inside the contractor organisation should follow the same control.