Planning tools

    Project: Commercial Plaza — Block A

    PCR No.: PCR-007

    Date: 25/11/26

    Originator: Project Planning Engineer

    Change: Add basement water tank and pump room

    Reason code: Client request — new or changed requirement

    DescriptionClient requested a 50,000-gallon underground water tank with pump room below the parking ramp.
    Scope impactExcavation, raft, RCC walls with waterstops, waterproofing, pump room MEP and backfill.
    Schedule impact18 days · critical path affected — support with a fragnet
    Cost impactDirect 7,850,000 + indirect 650,000 = 8,500,000
    Quality impactWatertightness test and waterproofing warranty required.
    Risk impactGroundwater at 3 m — dewatering needed; adjacent footing support.
    Options considered1) Approve as proposed. 2) Overhead tank only (no delay, lower capacity). 3) Do nothing.
    RecommendationOption 1 with dewatering by wellpoints; start after ramp excavation to keep 8 days of float.

    Prepared by

    Name / signature / date

    Project Manager

    Name / signature / date

    Engineer / Consultant

    Name / signature / date

    Client approval

    Name / signature / date

    Decision: ☐ Approved ☐ Approved with comments ☐ Rejected ☐ Deferred. Update the baseline, budget, drawings and change log only after approval.

    Uncontrolled change is the fastest way to lose time and money. A formal change request records what changes, why, what it costs in time and money, which options were considered and who approved it — before the work is done. This generator produces a clean, numbered PCR ready for signature.

    When to raise a change request

    Raise a PCR for any change to approved scope, specification, drawings, quantities beyond tolerance, sequence, milestones or budget — whether requested by the client, designer, consultant or contractor. Under FIDIC-based contracts, a variation is instructed by the engineer; the PCR is the internal and pre-instruction record that evaluates it.

    Reason codes

    Client request (new or changed requirement); Design change or development; Error or omission in documents; Unforeseen site condition; Regulatory or authority requirement; Value engineering proposal; Force majeure or external event; Contractor proposal for method or sequence. One primary code keeps the change log analysable.

    Impact analysis

    Scope: what is added, omitted or changed. Schedule: days of delay or saving and whether the critical path is affected (support with a fragnet). Cost: direct cost, indirect cost and contingency used. Quality and risk: new risks, approvals and testing. Resources: labour, plant and materials.

    Options and recommendation

    List the alternatives considered — including 'do nothing' — with their impact, then the recommended option and why. Decision makers approve faster when trade-offs are visible.

    Approval and implementation

    The PCR moves from originator to project manager, consultant/engineer and client. Only after approval are the baseline, budget and drawings revised and the change log updated.

    How to use

    1. Fill in project details, the change title and reason code.
    2. Describe the change and justify it.
    3. Enter time, cost, scope, quality and risk impacts and the options.
    4. Print the A4 PCR (sign-in required) and circulate for signature.

    FAQs

    Is a PCR the same as a variation order?

    No. The PCR evaluates and requests the change; the variation order or engineer's instruction is the contractual authority to proceed.

    Is my data saved?

    Drafts stay in your browser only. Nothing is stored on a server.

    Can I use it for internal changes?

    Yes — method, sequence, resource or budget re-allocation changes inside the contractor organisation should follow the same control.