    Measurement Sheet (MB) in Civil Engineering: Format, Deduction Rules, Joint Measurement & Billing Guide

    How to write a measurement sheet and MB entry: standard columns, units, IS 1200 deduction rules for masonry, plaster and concrete, joint measurement and a worked example, with a free format.

    C
    CM PRO Academy
    23 Nov 2026

    The Measurement Sheet, recorded in the Measurement Book (MB), is the record behind every bill in construction. Every quantity in an IPC (Interim Payment Certificate), every BOQ total and every final account must trace back to a line in it. If a measurement is missing or unclear, the payment is held up. This guide covers the standard format, how to write each entry, deduction rules, joint measurement and how the sheet links to the abstract and the bill.


    STEP 011. What a measurement sheet is and why it matters

    DocumentPurpose
    Measurement Sheet / MBRecords the measured dimensions of work actually done: location, number of times, length, breadth and height.
    Abstract of CostTotals the measured quantities item by item and multiplies them by BOQ rates.
    IPC / Running BillClaims payment for cumulative quantities, minus previous payments, retention and recoveries.

    In government work the MB is a legal record. Entries are made in ink, signed and dated, and never overwritten. Corrections are struck through and initialled. On private and international projects, signed joint measurement sheets do the same job.


    STEP 022. Standard measurement sheet format (columns)

    ColumnWhat to write
    Item No.The BOQ item number, exactly as in the contract.
    Description / LocationA short description plus the location, e.g. "RCC slab, Block A, 1st floor, grid A–C / 1–4".
    Nos.The number of identical members (e.g. 4 columns).
    Length (L)The measured length.
    Breadth (B)The measured breadth or width.
    Height / Depth (H/D)The measured height, depth or thickness.
    QuantityNos × L × B × H. Blank dimensions count as 1.
    Unitm³, m², m, kg, Nos, Cft or Sft. It is always placed immediately after Quantity.
    Remarks / Drawing Ref.The drawing number and revision, IR reference and photo reference.

    Dimension order: always write L × B × H in the same order so a checker can follow every line.

    Units by item type:

    • Volume (m³ / Cft): earthwork, concrete and masonry thicker than one brick.
    • Area (m² / Sft): plaster, paint, flooring, formwork and half-brick walls.
    • Length (m / Rft): pipes, skirting, railings and cornices.
    • Weight (kg / ton): reinforcement and structural steel.
    • Number (Nos): doors, fixtures and fittings.

    STEP 033. Standard deduction and measurement rules

    Measurement rules come from the method of measurement in your contract, such as IS 1200, which provincial C&W / PWD practice in Pakistan widely follows, or NRM2, CESMM4, POMI or the MES Standard Schedule. The figures below are the IS 1200 conventions. Always check the method named in your contract.

    Masonry (brick/block work)

    • No deduction for openings or voids up to 0.1 m² (≈ 1 Sft) each, for the ends of beams, purlins and joists, or for bed plates and lintels up to 0.1 m² in section.
    • Deduct openings larger than 0.1 m², lintels, RCC bands and embedded columns.

    Plastering and pointing

    • Openings up to 0.5 m² (≈ 5 Sft): no deduction, and jambs and soffits are not measured.
    • Openings from 0.5 m² to 3 m² (≈ 5–30 Sft): deduct one face only. Jambs and soffits are not measured.
    • Openings larger than 3 m² (≈ 30 Sft): deduct both faces, and measure jambs, soffits and sills separately.

    Concrete

    • No deduction for reinforcement volume, or for openings up to 0.1 m² in slabs.
    • At junctions, measure the slab full, then the beam below the slab only, then the column between floor and slab soffit. This means no volume is counted twice.

    Earthwork

    • Measure the bed area × mean depth from the original ground levels in the joint level book.
    • Lift and lead (carrying distance) are recorded separately when the contract pays for them.

    STEP 044. Worked example: plaster on a room wall

    The room is 4.0 m × 3.5 m, with a wall height of 3.0 m (inside face).

    DescriptionNosLBHQuantityUnit
    Walls, long sides24.00—3.0024.00m²
    Walls, short sides23.50—3.0021.00m²
    Deduct door 1.0 × 2.1 = 2.1 m² (0.5–3 m², one face)11.00—2.10−2.10m²
    Window 0.6 × 0.6 = 0.36 m² (< 0.5 m², no deduction)————0.00m²
    Total42.90m²

    STEP 055. Joint measurement procedure

    1. The contractor's QS notifies the Engineer or Resident Engineer when work is ready, usually through an IR / PRIR.
    2. Both parties measure together on site or from approved drawings.
    3. Both sign and date the sheet, and the contractor keeps a copy.
    4. If you disagree, record both figures with a remark and resolve the difference before the IPC.
    5. Hidden work (foundations, reinforcement and buried pipes) must be measured before it is covered. You cannot measure it later.

    Under FIDIC, Clause 12 (Measurement and Evaluation) says the contractor must attend the joint measurement. If the contractor does not attend, the Engineer's measurement is accepted as accurate.


    STEP 066. Common mistakes

    • No location or grid reference, so the line cannot be checked.
    • Unit missing or placed in the wrong column.
    • The same member measured twice, e.g. a beam measured through the slab depth.
    • Deductions not applied, or applied against the contract's method.
    • Hidden work covered before it was jointly measured.
    • Cumulative totals not reconciled with the previous IPC.

    STEP 077. Free CM PRO tools for measurement

    STEP 08Learn it properly, free

    Measurement, deductions and billing are taught with quizzes and a verified certificate in the Quantity Surveying course.


    STEP 09FAQ

    What is a measurement sheet in civil engineering? It is the record of the measured dimensions (Nos × L × B × H) of work done, item by item. It supports the BOQ quantities and interim payments.

    What is the MB? The Measurement Book. It is the official bound register in which measurements are recorded and signed, especially on government works.

    Where should the unit column be? Immediately after the Quantity column, so each quantity is read together with its unit.

    Do we deduct door openings in plaster? Under IS 1200 conventions, you don't deduct openings up to 0.5 m². You deduct one face for openings of 0.5–3 m², and both faces for openings over 3 m², measuring jambs and soffits separately. Follow your contract's method of measurement.

    What is a joint measurement? It is a measurement taken and signed together by the contractor and the Engineer. It is the agreed basis for payment.

    This is general guidance. The method of measurement named in your contract always prevails.